Expansion 2009
Overview of the project
- Phase I – Glass-paneled year-round swimming pool and new ice surface installed.
- Phase II – Renovate and rejuvenate existing facility, including mechanical, electrical, plumbing, and floors
Latest updates
- New Pool tanks are poured and glass panels appearing on outer structure around pool.
- New Pool Roof completed 21JAN10 (see below)
- New Pool Open - due May/June 2010
- New ice surface installed.
- All Ages and Junior Locker rooms well under construction.
- New Reception and Member Services COMPLETED May 2010
![]() |
|
|
|
|
|
|